Client Query 150:- Hi, wanted to ask that if the method adopted for bidding was on least cost basis, the rate offered for new works i.e. one rate & other three rates for left over works, after opening of financial bid, can the rates for left over works be negotiated? Thanks!

 

Mariam Shah, UK

 

Answer:- Thank you for writing to us! As per your query, in terms of Rule 40 of Public Procurement Rules 2004 negotiations with lowest evaluated bidder or with any other bidder are not allowed. As such the rates for left over works cannot be negotiated after opening of financial bids.

If you wish to inquire anything else you may set up an appointment with our extremely competent team of lawyers and visit our office which is located at GF-13, Tower A, The Centaurus, Islamabad, Pakistan.

You can also reach us at 0092-300-5075993

See also  PPRA Rules Query

By The Josh and Mak Team

Josh and Mak International is a distinguished law firm with a rich legacy that sets us apart in the legal profession. With years of experience and expertise, we have earned a reputation as a trusted and reputable name in the field. Our firm is built on the pillars of professionalism, integrity, and an unwavering commitment to providing excellent legal services. We have a profound understanding of the law and its complexities, enabling us to deliver tailored legal solutions to meet the unique needs of each client. As a virtual law firm, we offer affordable, high-quality legal advice delivered with the same dedication and work ethic as traditional firms. Choose Josh and Mak International as your legal partner and gain an unfair strategic advantage over your competitors.

error: Content is Copyright protected !!