2011 MLD 1402 LAHORE-HIGH-COURT-LAHORE

2011  MLD  1402     LAHORE-HIGH-COURT-LAHORE

ANJUM NIAZ CHAUDHRY

Versus

MANAGING DIRECTOR, SUI NORTHERN GAS PIPELINE LIMITED

S. 11—Constitution of Pakistan, Art. 199—Constitutional petition—Maintainability—Compressed Natural Gas (CNG) Filling Stations—Charging of excessive rates by Gas Supply Company—Contract entered between petitioner and company contained a clause for referring dispute to Authority for its resolution—Petitioner had not availed his remedy under such contract or S. 11 of Oil and Gas Regulatory Authority Ordinance, 2002—Constitutional petition filed without availing an alternate remedy would not be maintainable—High Court dismissed such petition accordingly.

 

 

 